Moradi M, Fatehimanesh K, Nouri Rahimabadi S M H. Determining the risk of critical activities in organizational life management system based on ISO 22301 standard (case study: Municipality of district 1of Tehran). jorar 2018; 10 (1) :45-59
URL: http://jorar.ir/article-1-472-en.html
Assistant Professor, Faculty Member, Department of Civil Engineering, Shahr-e-Quds Branch, Islamic Azad University, Tehran, Iran
Abstract:   (2717 Views)
Introduction: Paying attention to the operational processes of emergency or crisis management has widened in the country that can be cited the legal requirements of the prospectus document at 1404 horizons and the policies of the system related to establishing responsible organizations for crisis management. Business Continuity Management Systems (BCMS) with the requirements of ISO 22301 are factors reducing potential hazards for key activities of the municipality of Tehran. This research describes the standard challenges in the municipality of Tehran's district.
Method: This descriptive-applied research, crisis cases are identified by using questionnaires, interviews, and group seminars through Delphi method. In the following, by analyzing the consequences Business Impact Analysis (BIA) in four major missions such as safety, health, credibility of the organization and citizens' dissatisfaction, important events of crisis were identified using the relative weighting indicator. At the final stage of Delphi, the consensus reached its ultimate goal by assessing the probability of occurrence and severity of events, the unacceptable risk determines
Findings: The findings showed that the average score is more than mean, if the subject's score on the Likert scale is higher than the median, the attitude toward the subject is considered positive. At 99% confidence level, Kolmogorov-Smirnov test was significant (p-value=0.05). Therefore, a nonparametric test should be used. Spearman correlation coefficients were the largest among the research variables (0.559). In the risk analysis section, the risk number of disruptive events of vital activity was derived from the probability and severity of the event between 1 to 16.
Conclusion: By analyzing the outcomes of Business Impact Analysis ((BIA) from six main operating factors of organization services such as violation of laws, financial damages, environment, social and security consequences, organizational credibility, possible risk of any outcome at stopping the activity is calculated by considering the probability of occurrence and velocity of the event. In order to achieve the first priority of municipality activities, with the Delphi method, in several steps, priorities out of 208 critical activities fell to 56 and 38 respectively. Finally, a final agreement was reached on the 10 main activities. More important events for the first year include waste collection, snow removal, IT support services, emergency management, management of emergency response, and emergency services.The maximum number of risks obtained for the emergency event is related to lack of coordination between organizations, traffic problems, and blocking the roads, lack of preparation and earthquake above six Richter.
Full-Text [PDF 517 kb]   (1602 Downloads)    

Add your comments about this article : Your username or Email:
CAPTCHA

Send email to the article author


Rights and permissions
Creative Commons License This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

© 2025 CC BY-NC 4.0 | http://www.journalsystem.ir/demo5

Designed & Developed by : Yektaweb